Campaigners from Powderhall.Link presented at the November 2026 meeting of Leith Central Community Council, along with City of Edinburgh Council ('CEC') Transport & Environment Committee Convener Cllr Stephen Jenkinson.
Much was discussed, but the biggest turn out of new information came from a fairly candid presentation from — and questions to — the Transport Convener. We took fairly copious notes, offered below - these are not intented to be verbatim quotes, but capture the crux of what was being said as to the current state of progress and the future of the project.
Chris Hill gave a very solid overview and gentle prodding regarding moving forward.
Transport Convener Cllr Stephen Jenkinson speaking:
Credited Chris for very good summary / 'potted history'
Timeline involved is “kind of depressing”
A lot of the reasons are financial that’s why big projects, aspirational or not, get stuck
The Jacobs feasibility study looked at it as an Active Travel route because a lot of these big infrastructure projects require external funding, you’ve got to go where the money is
At the time the Scottish Government Active Travel Investment Fund had more money in it than currently, so a better chance of having a deliverable project out of it
Jacobs' Feasibility Study published in 2023, a lot of the details of the route, not just about cycle path but more usable space
One sticking point has been that this is as much about land acquisition and asset transfer / management, as delivering a project
The land ownership is split, with land predominantly owned by NR. DB cargo UK mentioned as owning some of the land
Assets are not just bridges, but walls, culverts etc too. For the council to take these on, they have to be at an adoptable standard and they need to know what they’re taking on.
CEC asks, essentially, what kind of risk are we looking at here?
Officers said £10m (for risk ballpark?) - nobody really knows what the risk is right now
Assets in ownership of Network Rail ('NR') total 33 — ‘a lot’ of structures
Because CEC take on maintenance, they need to make sure before they take on the whole asset collection that they understand the risk. Take on a bridge, it falls down, you’re on the line to fix it
Still in a period of negotiation, and need to commission a proper structural survey the most up to date position is they’ve agreed to split the cost of the survey of assets with CEC 50/50, but NR have only committed to a ceiling of £25k
Officer assessment is north of £100k for the survey and 12 months to undertake it
Still negotiating on how to split the cost of doing this structural survey on the assets.
1. NR fix everything up would be glad to see the back of it and its assets
2. Problem comes if NR aren’t interested in doing that, land transfer for free but potential tens of £m down the line in liabilities for fixing structures
Land acquisition from NR itself, would be relatively straightforward;
DB Cargo UK are happy to hand over, as long as they have an idea of what is planned
Risk for structures is the sticking point
Important to mention; this route whether it’s AT or anything else, it does sit within the Local Development Plan, which the Scottish Government signed off; is it likely to make the cut for the 2040 plan too
Financing of any development is the hard part
If the structures were fine, and the land acquisition was for free, it’s still a £10-15m project in the whole. CEC has managed to get around £14.5m per year in AT funding. So this one project would take the whole budget
Mentioned the West Edinburgh Link costs more overall, because single year funding means delivering it in phases
The Powderhall Link did appear in the SNP manifesto, but when the letter asked what will you do to help, the answer appears to be “not an awful lot”. So back where we are
Can’t assess risk fully due to cost, no finance (yet) to fund it as an overall / whole project
Harald Tobermann asks; would you (Labour) support the project, were the ducks in a row?
Cllr Jenkinson:
Yes and it would fair to say that’s already started. To be absolurely honest, the Scottish Government Active Travel budget has only been going one direction for years, and I don't see it changing short term - the project needs to be redefined
Needs to become a public realm project
Maybe further down the line, leveraging Visitor Levy funding for it as a public realm project
The scale and size means external funding
A gentleman asked: If it’s £100k, but negotiating with NR is only to get £25k, is it worth cracking on and avoiding further delays?
If NR want rid of the asset, it’s not fair to pass on all this risk for example if they’ve not been maintaining structures
Need pressure on them to negotiate
Officers are keen to assess
There will be a Report back to committee, though will Jenkinson still be convener, he wondered
Ben from edi.bike asked: Given the challenges of multi-year funding and for example the carving up of the West Edinburgh Link into shorter sections, single year funding must mean delivering the Powderhall Link in shorter sections it was of course a rail line, so shorter projects like station to station might make sense to establish usable links?
Cllr Jack Caldwell:
Not seen anything with so much cross party consensus
Engaging with residents associations along the line, now having regular meetings with NR and an asset survey ‘has been procured’
Worth remembering when officers are non-committal at TEC, there are negotiations ongoing so he would hope they are coy!
PL made the cut for the City Mobility Plan / CMP capital investment programme
Sources of funding section 75 contributions are worth exploring, with e.g Macdonald Rd ‘site/opportunity 22’ including requirement for link to Powderhall Active Travel Link - what can council squeeze out of other section 75 contributions…
Agrees we lose something if we only think Active Travel referenced Roseburn path and linear parks as a concept, in Leith nature access is at a premium;
Constructive working relationships across all groups
But could improve on how CEC is reporting progress back to stakeholders
New Town & Broughton CC rep: CC has not discussed but would be amazed if not in favour. Shared concern that progress sorting St Marks Park Bridge must not be held up due to progressing the Powderhall Link
Meadowbank Craigentinny CC shared positive remarks about support for the project.
Stockbridge CC rep - CC boundary brings down one side of Chancelot path leading to PL, anything that helps connect up the active travel network we would support, and will bring to meeting on Wednesday
Harald Tobermann referenced update from Ben Macpherson MSP. In the ‘Early stages’ of pushing for it (election was only in May). Had a call with DB Cargo UK… Mentioned MSP dialogue with Councillors Danny Aston and Jack Caldwell. Broadly supportive.
Chris asked we were under the impression a survey had been on since January this year as reported; SJ says not yet. (Could this be different types / depths of survey maybe?)
Harald Tobermann big figures are always bandied about (e.g. St Marks). Seconded the notion from CC Chair that all parties should put the Powderhall Link in their manifestos for 2027… (edi.bike noted: councillors promising things there’s no money from Government for, won’t manage to deliver them)
CC chair, thanks for coming and giving clear explanation.
The Community Council subsequently moved and voted through a motion in support of the route:
"To support a staged Powderhall Green Corridor between Piershill and the North Edinburgh Path Network, creating both an off-road connection and “a vital and valuable green open space to be enjoyed for its own sake”.
...with several representatives from other adjacent Community Councils also expressing their support at the meeting.